Start the Hard Parts First

David Ackerman, CEO of ACG
David Ackerman
5 min read
Straight cords to a mess

Your construction schedule depends on work that starts before design is complete. Permit preparation, environmental review, railroad coordination and material planning each need time. If those workstreams wait until the drawings are finished, your planned start date may already be at risk.

The challenge is knowing what can move forward now and what needs more information. Start by identifying the dependencies that control when construction can begin. Then give each one an owner and a next step.

Find Out What Each Application Needs

A preliminary route gives you a place to start the permitting conversation. Before treating that route as ready for submission, confirm what the reviewing authority needs to evaluate the proposed work.

Ask which drawings, surveys or environmental information belong in the application. Find out what the team can prepare alongside design and what depends on a more developed alignment. An early conversation helps you plan a complete submission without guessing at the requirements.

A late application can delay construction when the work depends on that approval. Work backward from the planned construction date, using the reviewing authority’s guidance to establish the submission target. Record the assumptions behind that date and revisit them as the project develops.

Start Coordination Before the Deadline

Federal land, state land and railroad crossings deserve attention during planning. Identify the responsible parties and ask what coordination the proposed work requires before setting the schedule around an assumed approval date.

For federal land, ask the managing agency about the review process, environmental information and any studies needed for the proposed work. For state land or highway crossings, confirm the relevant agency’s submission and construction requirements. For railroad crossings, check the engineering review, access arrangements and construction specifications.

Engage Tribal governments early so their priorities and requirements inform the plan. Confirm the applicable consent and approval process with the Tribe and, where appropriate, the Bureau of Indian Affairs.

These conversations should produce more than a contact name. Your team needs to know what to prepare, who will prepare the information and which decisions must happen first.

Check Material Lead Times Before Committing

Talk with suppliers while design is underway. Confirm current lead times for the materials your project expects to use and ask which items need an earlier decision.

You don’t need a final bill of materials to begin that conversation. You do need enough certainty about specifications and quantities before placing an order. Ask about quote validity, delivery windows and the cost of changes or cancellations.

Use those answers to decide when a purchase makes sense. Ordering early may protect the schedule, but an order based on unresolved design assumptions can create avoidable costs. Make the tradeoff visible to whoever owns the budget.

Apply the same discipline to construction capacity. Discuss availability and scheduling flexibility with contractors early, then confirm commitments as approvals and scope become clearer.

Turn Early Conversations Into a Working Schedule

Starting the hard parts first doesn’t mean starting everything at once. Focus on the dependencies with the longest lead times or the least flexibility.

For each dependency, record:

  1. The work or decision that must happen before construction can proceed.
  2. The information needed to move that work forward.
  3. The person responsible for the next step.
  4. The target date and the assumptions behind that date.

For example, a railroad crossing may depend on engineering details that the design team hasn’t completed. The immediate task is to confirm the railroad’s requirements and schedule those design details. Submitting an incomplete application won’t resolve the missing information.

Review these dependencies as design progresses. If a requirement or lead time changes, update the schedule and identify which downstream work is affected. That gives the team a basis for adjusting the plan before crews or materials are waiting.

How ACG Helps With Sequencing

At ACG, we help rural and Tribal broadband teams connect engineering decisions with construction readiness. Reviewing a proposed route for permit triggers and coordination needs helps identify which work should begin alongside design.

The goal is a plan your team can act on, with clear ownership of the next steps and fewer untested assumptions about when construction can start.

Know What Needs to Move Next

If your project is in planning, review the dependencies behind your construction date now. Which ones have an owner and a confirmed next step? Which still rely on an assumption?

Bring your proposed route, target construction date and unresolved questions to ACG. We can help you identify what needs attention first and what information will support the next decision.